FHWA Project 475980-00001
Pavement Marking Demonstration Projects: States of Alaska and
Tennessee
Safety
Study - Update on Crash Surrogate Study
2007
Before Data - Speed and Lateral Placement
February
2008
All
of the before data, including the vehicle tracking, has been completed.
Preliminary analysis should start in the March and April timeframe.
Scheduling for the April data collection and curve restriping
started this month.
December
2007
The before data reduction was completed, but the tracking task
was still not complete. The data can be viewed through the link
above, which also contains restriping information.
During the
preparation to set project limits for restriping the study curves,
several things were determined. First, it was decided to only
restripe the treatment site curves with 6-inch wide edgelines,
provided that the spring retroreflectivities were not too low,
and that restripe retroreflectivities were kept within a range
of 200 to 300 mcd/m2/lux. This was decided to avoid one of the
problems with restriping contracts, which is inadvertently creating
a wider line from difficulties with restriping directly over the
existing marking. This problem was evident in the fact that the
average edgeline marking width from each curve ranged from 4 to
6 inches. The restriping retroreflectivity range was set to minimize
confounding the impact of line width with retroreflectivity. If
the spring retroreflectivity values are below 150, then, additional
curves may be restriped. If control site curves are restriped,
they will be restriped with 4-inch wide edgelines. Second, it
was decided to add one additional curve to the data set to help
round out the study design. The before data for this curve will
be collected in early April prior to restriping this curve. With
the concern over the spring retroreflectivities, the field team
that collects the before data for the 19th curve will also collect
spring retroreflectivity measurements for all of the curves.
September
2007
The
research team completely reviewed all of the initial data, and
was still in the process of reducing the data for analysis. It
was projected that the data reduction will be complete in December
of 2007. The reduction process included developing various macros
to efficiently reduce the data from its raw format into individual
vehicle speeds and lateral positions as tracked through each counter
in each curve. Then, manual spot checks of the reduced data were
conducted to verify the proper reduction by the macros.
Simultaneously
while the data reduction was being conducted, the research team
was putting together restriping project limits for each of the
curves to be submitted to TDOT by the end of the month. The research
team continued to be in direct contact with TDOT, and the team
had been told this timeframe will be adequate to ensure the curves
are restriped prior to the after data collection period during
the summer of 2008.
August
2007
The
research team completed the data collection of the before-data
at the 18 curves in Tennessee. The research team then began the
data reduction process.
July 2007
The
research team continued collecting data at the 18 curves. To this
point, the research team had been able to collect data at 4 curves
each week.
June
2007
The
research team traveled to Tennessee on July 9th to collect the
before data at the 18 curves. The plan was to visit at least 4
curves a week, and barring weather or equipment issues, complete
the data collection by August 10th. The research team also met
with Jim Maxwell of TDOT to start coordinating the restriping
of the study curves for next summer. At the time, it was planned
to install pavement markings that are 2 inches wider than the
current markings. If the current markings were 4 inches wide,
they would be restriped with 6 inches; if they were 5 inches wide,
they would be restriped with 7 inches, etc. The curves will be
restriped from approximately 500 feet prior to the warning sign
all the way through the curve in each direction. Hence, the centerline
restripe will be the length of the curve plus approximately 1000
feet. The centerline will be restriped with 4-inch wide markings.
May 2007
A
researcher traveled to Tennessee to visit the 18 horizontal curves
to be used during the field testing of wider edgelines in the
safety portion of the FHWA 1907 project under SAFETEA-LU. The
researcher, accompanied by three TDOT staff members, verified
what the appropriate advisory speed and/or curve warning sign
should be if required in each curve based on the MUTCD. It should
be noted that the 10, 12, and 14 degree ball-banks readings were
used rather than the current 16 degree ball-bank reading as stated
in the 2003 MUTCD. This was done because the current 16 degree
ball-bank is being reviewed. After driving all 18 curves, the
researcher found that 14 of the 18 curves required either adding
an advisory speed or reducing the current advisory speed, and
only 2 of the 18 curves neither required an advisory speed or
warning sign. Only 4 of the curves initially had advisory speeds
posted while 14 of the curves had warning signs. In addition,
2 of the curves that do have warning signs do not require them.
They were left because it was felt there may be some crash history
and/or local complaint that required it. Another point to note
is that 2 curves are located within winding road segments, but
this is not considered a problem because the speed limit was 35
mph, the advisory speed was 30 mph, and the tangent approaches
allowed for at least 10 seconds of approach prior to the PC.
Update
on Multi-State Retrospective Crash Study
Safety
Study
Durability
Study
PM
Demo Main Page
|